24km Hdp 315mm Pipeline Water Network & Pumping Station For China Petroleum Engineering Construction Habshan Camp, For Adnoc Bab Integrated Facilities

24km Hdp 315mm Pipeline Water Network & Pumping Station For China Petroleum Engineering Construction Habshan Camp, For Adnoc Bab Integrated Facilities

  • Client : client name
  • Date : DD/MM/YYYY

Design , ADDC approval , Supply and Installation of 24.5 kilo meter DN 315mm HDP pipeline as per ADDC regulations. Water demand approval from ADDC for 316,800 Imperial Gallon per Day. Water network Hydro testing, Disinfection , Testing & Commissioning for 24.5 kilo meter DN 315mm HDP pipeline including Pumping ststion to China Petroleum Engineering and Construction Corporation Camp. Safe and secure water to drink for 7,000 persons